lower don trail

Another Toronto infrastructure project is now more than a year behind schedule

Residents who have long complained about the state of one of Toronto's most popular and scenic multi-use trails continue to wait for the City to complete a massive overhaul of the amenity for more than a year now, and additional delays have just been tacked on to the project timeline.

The Lower Don River Trail, which spans nearly 13 km through lush green space alongside the Don River, is one of the few places where you can immerse yourself in nature without leaving the heart of the city. However, a significant downtown segment of the trail has been off-limits to the public since the spring of 2023, when crews began renovation work that was only supposed to take just over a year.

Unfortunately, as with many infrastructure projects in Toronto, the pathway's summer 2024 reopening date came and went, with City staff finally announcing in August that the big debut of all the improvements was being moved almost an entire year, to July 2025.

Now here we are, at the end of July, and still no revamped Lower Don River Trail.

To its credit, the City did warn the public right off the bat that things were not shaping up as anticipated, writing in a June 2023 update — just one month into the work — that site preparations were "taking longer than anticipated due to irregular topography and approvals and inspection for the permit conditions."

Another update that November also reiterated that the process was delayed further due to erosion and "challenges with getting materials and equipment in and out of the site." But, as of October 2024, the opening was still projected as July 2025.

The project page now lists multiple stages of ongoing work that will stretch through this summer and into the fall, including installing stair and ramp components, landscaping for stormwater management, repaving, and adding fencing.

While there were rumours that the fencing may come down by August, the page now provides a September 2025 opening for the section of the trail that runs between the Bala Underpass and the Queen Street Bridge, and a November 2025 opening for the remainder, all due to setbacks ranging from poor soil conditions to "challenges working within a narrow work area between the Don River and Metrolinx tracks."

"The project not only involves trail construction but also complex structural ramp and stairs installation, and requires deep footing to bedrock to support the structures. But once complete, it will offer a lasting experience for the community that improves accessibility," the City reassured locals in yet another update last month — the first one since October 2024.

But some are having a hard time seeing the vision when parts of the trail still look like a muddy, treacherous mess, and after multiple holdups.

Here's hoping this most delay is the final one before a fall 2025 launch, though we perhaps shouldn't hold our breath.

Lead photo by

City of Toronto


Latest Videos



Latest Videos


Latest in City

Viral map has internet divided over opinions on Toronto and the GTA

Here are some things only someone from Toronto would truly understand

Toronto's new linear park under rail line still has long way to go before opening

Multiple road closures to make for a weekend of nightmare traffic in Toronto

Lobster-like invasive species linked to ecosystem havoc now confirmed in Ontario

Ontario's enormous U.S. border bridge won't open this week as planned

These stretches of the TTC subway might be brutally slow during FIFA madness

These are the road closures in place on FIFA match days in Toronto