toronto trails

Popular Toronto trail will stay closed for another year as construction drags on

One of Toronto's busiest multi-use recreation trails is currently undergoing a major revamp, but much of the excitement walkers and cyclists had about its forthcoming reopening has likely now been dashed by multiple construction delays.

The Lower Don Trail, which spans all the way from ET Seton Park down to Corktown Common, will sadly remain partially shuttered to the public for another entire year until July 2025, according to the latest update from the City.

While the first phase of remediations of the path were completed in 2017, work has been intermittent, restarting again with gusto in May 2023. The latest hiccup, discovered in the fall but newly announced, is "poor soil conditions."

Residents who have complained about the state of the trail in the past can agree that the improvements — which include erosion and flooding protection, drainage fixes, accessibility upgrades and enhanced connections — are necessary, but many have expressed frustration this season with how long they're taking.

To be fair, the City gave hints that slowdowns were imminent from the get-go, writing one month into this phase of work in June 2023 that site preparation work was "taking longer than anticipated due to the irregular topography of the site and approvals and inspection for the permit conditions."

Through last summer, asphalt, trees, fencing, foundations and more were removed, leaving a muddy mess that anyone could see would not be cleaned up by the end of the year. Then came the the first major delay in November, pushing the completion date to "late summer 2024."

"The project site is complex, narrow and located between Don River and a rail corridor, resulting in some challenges with getting materials and equipment in and out of the site," the City wrote at the time.

"Additionally, a section of the site experienced erosion from the nearby river (a geotechnical review for a solution is underway), and some of the required permitting and approvals from other infrastructure located nearby took longer than anticipated."

Now come even further delays as the segment of trail between Pottery Road and the Bala Underpass, which was due to reopen this summer after more than a year of work, is set to remain closed for yet another year.

This May, the project page was updated with an extended timeline to summer 2025, reading "while [foundation] work will continue through winter 2024/2025, other landscape and site restoration work will need to be completed in spring 2025 because it cannot be done during the winter. With construction ongoing until July 2025, the active construction site will stay closed for public safety."

"The City continues to work closely with the contractor to identify opportunities to complete the work sooner and investigate where work can be phased to allow for earlier opening at sections of the trail, if feasible," it continues, adding that the timeline is subject to change in either direction.

The Bayview Avenue Multi-Use Trail, running parallel to the Lower Don, is being suggested as an alternative route for the entire distance of the closure.

Lead photo by

City of Toronto


Latest Videos



Latest Videos


Latest in City

Viral map has internet divided over opinions on Toronto and the GTA

Here are some things only someone from Toronto would truly understand

Toronto's new linear park under rail line still has long way to go before opening

Multiple road closures to make for a weekend of nightmare traffic in Toronto

Lobster-like invasive species linked to ecosystem havoc now confirmed in Ontario

Ontario's enormous U.S. border bridge won't open this week as planned

These stretches of the TTC subway might be brutally slow during FIFA madness

These are the road closures in place on FIFA match days in Toronto