Saturday, May 26, 2012Mostly Cloudy 24°C
City

What went wrong on Roncesvalles?

Posted by Tomasz Bugajski / March 29, 2011

Roncesvalles ConstructionWhat started as an enthusiastic attempt to beautify Roncesvalles (and replace some very old sewer pipes) turned into a major inconvenience for residents and businesses long ago. And the project, which began in 2009 and was supposed to end by 2010, is still not complete. Delays have ushered in another round of construction this spring.

The expected completion date is now July 4th. This time the pressure to finish is strong — it's the third construction season and the Polish Festival is scheduled to begin in mid-September. To say that locals want to be able to celebrate without the presence of orange fencing and abandoned tools would be an understatement.

Sanscon Construction, behind much of the work on St. Clair, is blamed by some residents and members of City Council for mishandling the project. And many business owners are calling for compensation from the City for lost business. Area councillor Gord Perks hopes to make the necessary reforms to prevent delayed construction in the future.

I recently had a chance to ask Perks about why the project has dragged out so long and whether or not the new completion date is realistic. Here's what he told me:

What went wrong on Roncesvalles?

It's very simple what went wrong on Roncesvalles, the contractor chose not to put enough resources in the job to get it completed on its deadline. There were a certain number of days to complete the contract and he hasn't met them. That means he's now paying some penalties, and I don't think those penalties are adequate.

Sanscon was the same contractor that did the St. Clair construction, which also ran into problems. Why did they get hired again?

He did part of St. Clair West? Oh yeah, he did. Well, the problems on St. Clair West had nothing to do with him. The problems on St. Clair West came from a few factors. One of them was that they were making changes as they went. If you're marshaling the correct skill-set and equipment to go work on a street, and then all of a sudden "no, no, we have to bury these wires, so we have to stop everything," your costs and timing go out the window. So the work that this guy would have been doing wouldn't have been the cause of the problems on St. Clair West.

Because of the history of the way road work is done in the city of Toronto we're bound by a couple of problems. One is that it's a privatized service, so these are not municipal employees and we can't just tell them "you're falling behind, bring in five more guys, and get the work done." That's one problem with privatized services, you can't control their day to day decisions.

The second problem is because of a long history of people to the right of centre arguing that everything costs too much. We are required to take the lowest bid on a contract, so it doesn't matter what your history is on completing other work for the City of Toronto, so if you're a licensed, competent, legal bidder, we're sort of required by law to take you as the guy who wins the bid.

So unless he does something to disqualify himself from bidding on contracts, I'm not sure how legally you can prevent him. There is talk about bringing a report from city staff that gives council more control over how to disqualify people. I'm certainly keen to have that conversation. I've actually pulled together a group of people from the community who've been intimately involved in the construction and the design and that's one of things we're going to talk about, but I can't prejudge it. Another thing about the bidding process is that councillors are legally prohibited from participating in the selection of the winning bid, in order to prevent the kind of corruption that MFP left.

Will the construction be finished by the Polish festival?

It better be. I'll kill them if it isn't.

Lead photo by Rick McGinnis

Discussion

80 Comments

Sean / March 29, 2011 at 01:07 pm
user-pic
Personally, I do not think this is a Roncesvalles or even a Sanscon Construction problem. The city seems to be too willing to let construction projects drag on. The city needs to get its shit together. If the average person was allowed to function at their job the way the city does or the way the city allows people to do, they would not have a job for very long.
parkdaler / March 29, 2011 at 01:10 pm
user-pic
So in essence, if a vendor gets a contract with the city of Toronto, there is nothing that any municipal official can do to ensure that vendor meets the deadline except issue financial penalties.

"We are required to take the lowest bid on a contract, so it doesn't matter what your history is on completing other work for the City of Toronto, so if you're a licensed, competent, legal bidder, we're sort of required by law to take you as the guy who wins the bid"

As well, contracts can be awarded regardless of past performance on other city projects, unless a vendor screws up royally...

so basically, anyone who's got a valid set of credentials to bid on a City of Toronto project can f*** city residents royally.

our tax dollars hard at work. Keep up the hard work City of Toronto Procurement..doing a fine job at the moment.
Ubisu Design / March 29, 2011 at 01:10 pm
user-pic
Yikes! Looks like a big mess.
www.ubisu.com
Matt replying to a comment from Sean / March 29, 2011 at 01:31 pm
user-pic
Did you even read the interview? Perks explained that part of the problem is precisely that the city is legally powerless to prod the private contractors along, even if they want to. Which is another reason that contracting out to the private sector can be very troublesome.
Rich / March 29, 2011 at 01:34 pm
user-pic
Seems like kickbacks are alive and well in the bidding process... how can you award a contract to a company that hasn't lived up to its previous contracts? Thats not just mismanagement, thats a good indication of a little cash being given on the side.

Rick Kogucki / March 29, 2011 at 01:34 pm
user-pic
I'm a resident in the Roncesvalles neighbourhood. Our street runs off of Roncesvalles. Another aspect to this construction is that for the past three years the road has been torn up to replace the streetcar rails. Despite the fact that this work was just done, they go ahead and tear up the new(ish) tracks and concrete to work on the sewers. A complete waste of money. Who is doing the planning here? You can't blame the construction company for that.
steve replying to a comment from Sean / March 29, 2011 at 01:35 pm
user-pic
Uh... Did you read the entire article?
Tuzanor / March 29, 2011 at 01:39 pm
user-pic
The private company needs an incentive to provide the service correctly. Financial penalties may exist, but they're obviously not the cost of hiring more people to get the job done.

If the city wanted to be serious, it (if it's allowed) would tender the process with payments ongoing as objectives were met. If an objective isn't met in a timely fashion, the company doesn't get paid (even for work already done) and a re-tender is put out to complete the work. This basic incentive may delay projects now and then, but companies will be more careful in the long term when tendering and completing projects at the risk of doing work for no pay.
Butterfried / March 29, 2011 at 01:43 pm
user-pic
This isnt the first project, nor the last, to run behind schedule.

Just deal with it. Stop complaining.

Or sell your home and move to the 905.
Sean replying to a comment from Matt / March 29, 2011 at 01:43 pm
user-pic
If you read the article, you will notice that Perks discusses the fact that the process needs to be reformed. The city is not powerless. It should have fixed this a long time ago. This is not a new issue. It is one that has been seen in countless places all over Toronto.
Trev / March 29, 2011 at 01:45 pm
user-pic
I'm certain that isn't a threat made by Mr. Perks in this instance, but that's rather unprofessional behaviour for a city councillor.

Stop laughing, there is such a thing.
Bonk / March 29, 2011 at 01:46 pm
user-pic
Here it is eleven years into the new millennium and the city hasn't learned how to prevent lousy contractors from winning new bids even if their track record sucks the plastic bag?

"There is talk about bringing a report from city staff that gives council more control over how to disqualify people"

In the meantime jerkbag contractors will happliy zip Toronto taxpayer money up the DVP to their 905 mansions laughing all the way.
jackie / March 29, 2011 at 01:47 pm
user-pic
While I appreciate the candor, it is completely inappropriate for a councillor to say "I'll kill them" in an interview.
qwerty replying to a comment from jackie / March 29, 2011 at 01:53 pm
user-pic
He is a city councilor, so he won't live up to what he says.
Stra / March 29, 2011 at 02:02 pm
user-pic
the east side of the walk along Roncesvalles is interlocking brick which is already starting to shift and create many hazards. I can't believe they elected to do the walkway this way. Brainless. This whole project has been a mess from day 1.
ttraveller / March 29, 2011 at 02:03 pm
user-pic
I live on St. Clair and I have decades of experience in the construction industry. All the quality construction companies know that dealing with the City of Toronto is like entering a screaming nightmare world run by 6 year olds. The tender bid specs are nursery school level; you wake Monday mornings to "stop the clocks, we forgot to deal with this/that issue;" co-ordination between the countless levels of government and bureaucracy is non-existent; and to top it off you have politicos tied into their favourite expert "consultants" who wouldn't know a dollar from a hole in the wall. St. Clair, Bloor, Rosces, Toronto Housing Corp, and onwards. Ronces I wish you luck. This the job Ford has taken on.
Matt / March 29, 2011 at 02:08 pm
user-pic
I live in Roncy and I think this is getting blown out of proportion a little bit. People love to complain, but a 25%-35% time overrun on 2-year job that involved a lot of one-off, non-standard designs is just not that terrible. It could be much much worse. And while I'm sure businesses are suffering, the only ones that have closed were either terrible to begin with (e.g. Buddha Dog, Second Cup) or they closed for other reasons (e.g. Queen of Tarts, Silver Spoon). That's as far as I know, anyway.

Since construction started we went from having one mediocre sushi restaurant to three sushi restaurants -- one of which is great!

Since construction

Cliff S / March 29, 2011 at 02:10 pm
user-pic
The city needs to reform the failure to perform penalties. It seems like all they have is a small stick.

They need a big stick and carrots.

If the contractor comes in on time, then they get paid the bid amount. If the project is completed early then a bonus should be paid (%age of the total contract value, which would increase the earlier it's completed). Penalties should also increase with the amount of time that the contract runs over the projected timeline.

This built-in incentive/penalty should be mandatory for all road and public infrastructure projects that effect transportation infrastructure and local neighbourhoods.
lowrez replying to a comment from jackie / March 29, 2011 at 02:12 pm
user-pic
Oh, shut up.
lowrez replying to a comment from Butterfried / March 29, 2011 at 02:13 pm
user-pic
Ahahaha look at this idiot right here.
... replying to a comment from steve / March 29, 2011 at 02:14 pm
user-pic
Did you read the article?
Alvin Bowling / March 29, 2011 at 02:17 pm
user-pic

Most construction contracts apply a "large" daily fine on contractors that can't keep their contractual agreements. It's obvious these guys are stretched way to thin do contracts this big. In the future check to see if they actually have the equipment and manpower, that's a start anyway. These guys are
just screwing around at our expense, make it "their" expense in the future please!
Mikey / March 29, 2011 at 02:37 pm
user-pic
Any word on where Perks stands on compensation for business owners? I realize that the city doesn't really have any money to give them but I'd be interested to hear if he has any kind of alternative solution.
Sean replying to a comment from jackie / March 29, 2011 at 02:43 pm
user-pic
http://www.thefreedictionary.com/joke
mike in parkdale / March 29, 2011 at 02:45 pm
user-pic
sadly, the ongoing bullshit of Roncy has forced some of my favorite spots to go under.

People need to understand that this project was never just 'fixing a road' - it was the heart of a community, and needs to be treated like the living thing that it is.

A friend who had to mothball his business saw weeks go by with heavy machinery just sitting there with no one to use it. There were interruptions in water service that lasted way longer then they needed to be. When a big project like this takes place in the heart of a neighborhood, it has to be treated differently from a 'plow and pave' job in the middle of nowhere
Don / March 29, 2011 at 02:51 pm
user-pic
Speaking as one who lives in the Roncesvalles neighbourhood, I'm ok with the state of the construction and understand the delays... so far this project has been proceeding much more successfully and transparently than the St. Clair mess. As others have said a moderate overrun is almost par for the course in any kind of complex contract. Let's let them get on with it.

Gloria / March 29, 2011 at 02:58 pm
user-pic
Councillor Perks is an unusual person. As a taxpayer I want the cheapest bid, or should we go for the highest? I used pay invoices for work done at a purchasing dept at the Ministry of Government Services where the tenders were out of date, and I worked with a mother and son team and the roommate of the mistress of the general manager and anyone in purchasing could just pick up the phone and order goods and services withtout authorization. 1/4 to 1/3 of the invoices that came in had no bill of lading or purchase order attached. Would Councillor Perks prefer this system to the lowest bidder? So his answer is that he would kill the company representatives?
Mark Dowling / March 29, 2011 at 02:58 pm
user-pic
Perks is using this as a way to criticise contractors, when he says off the top that completion penalties are insufficient to incentivise the contractor to ensure enough resources are available. I'll grant him the point on tendering, but he should take the penalties issue up with a councillor who Ford bothers to listen too - that said he could have done it under Miller and didn't.

The problem is that the City wants to do 5 things at once - replace water, replace gas, bury hydro, rebuild streetcar track, redo sidewalks - but this is plainly a Roads Department incapable of walking and chewing gum at once.
Kate replying to a comment from Stra / March 29, 2011 at 03:00 pm
user-pic
The sad thing is, it's not "already" starting to shift. It was never done properly in the first place. Apparently they've re-done certain parts, but without much improvement.

Jesse / March 29, 2011 at 03:02 pm
user-pic
At least it's wrapping up. And the new renovations look amazing. It's also nice knowing that if you're a resident of Roncesvalles your streets won't need any new repairs for many years. Let's party!
ttraveller replying to a comment from Alvin Bowling / March 29, 2011 at 03:06 pm
user-pic
On St. Clair (where I live) they had to demolish and reconstruct the entire project 3 times. It's got nothing to do with the size of the penalty. It's about powerless, skillless bureaucrats running 100 million dollar projects and answering to politicos and their "independent" consultants and union masters, who don't give a hoot about the cost. And give even less of a hoot about the citizens.
jerry / March 29, 2011 at 03:12 pm
user-pic
lowrez In replying to a comment from jackie / MARCH 29, 2011 AT 2:12 PM

Oh, shut up.
---------
lowrez In replying to a comment from Butterfried / MARCH 29, 2011 AT 2:13 PM

Ahahaha look at this idiot right here.
---------

How come BlogTO is leaving these comments up?

They clearly violate the comment policy.
Rich replying to a comment from Jesse / March 29, 2011 at 03:13 pm
user-pic
People like you make me laugh....

I mean, if they can't do it right in 3 years above ground I'm sure EVERYTHING is kosher underneath. FOOL
Monty replying to a comment from Rich / March 29, 2011 at 03:32 pm
user-pic
Well Rich it appears that they are digging up and replacing some pipe on the west side south of Howard Park. I was under the impression that this part of the project was completed and it was supposed to be only the above ground work to be completed.
Also in the same area the curbs are now too close to the streetcar track to allow parking on that stretch of road. Really wonder how all the business owners in the area feel about losing more that 50% of the available parking on the street.
Councillor Perks, any idea?
k386 replying to a comment from Monty / March 29, 2011 at 03:38 pm
user-pic
The work on the west side is the Enbridge gasline replacement, this was shelved due to scheduling on Enbridge's part.

I am curious about the west side curb though, I can't count the number of times that I've heard the streetcar blaring its horn and blocking traffic while waiting for someone to move their vehicle.

Though I wonder if that was more due to the snow on the west side, and the inability to properly clear it due to that road block at Howard Park
oldsalty / March 29, 2011 at 04:23 pm
user-pic
The stretch in front of the Revue Cinema is the biggest blunder. It is a full city block (West side) that has been designed to prevent any parking whatsoever. Parking in front of those stores and restaurants is the most natural and expected thing to do. When people do what they expect they can do - they end up blocking the streetcars. I can't imagine what the purpose of preventing parking on that stretch is. It can't accomododate drop-offs or idling. We are lucky to have mixed commercial spaces on this street and I am disapointed with the design choices that were made at the expense of business owners. I fear that the design process was hijacked by those divorced from the reality that businesses need customers and customers need to drive (and park) cars. Not everyone can take a stroll to and from home with a shopping cart.
mike / March 29, 2011 at 04:24 pm
user-pic
This will be common if Ford get his privatization wish. Now if you have a problem with garbage pick up you can call the city. Private companys will not care as much as time is money and you cant cut into their profits. Same will happen will anything you privatize.

With Roncy it had some bad luck but in the long run the street will be much better then it was before. The work needed to be done. This is from someone who lives along St Clair. The street is lightyears better then it used to be

J.S. replying to a comment from Monty / March 29, 2011 at 04:32 pm
user-pic
Roncesvalles did not lose 50% of its parking. When the construction is over, it will have lost 18 spots out of 230, or 8%. Also, the streetcar delays have been caused by idiots parking alongside an unfinished TTC stop, in an unpainted bike lane that is also a no-stopping zone.

Roncesvalles should be judged when it is finished, not while everything is still under construction. Having accurate facts also helps.

I think the street is looking great, and I can't wait to see it finished!
gloria / March 29, 2011 at 04:42 pm
user-pic
I am sure that the merchants who are still left on Roncesvalles and St Clair are very grateful for the construction and are taking it in their stride.

I actually had a great deal of trouble getting city garbage pickup before the big bins came in. I work long hours and the neighbours reported that city employees were tossing my blue boxes around and smashing them. Some disappeared. I had to complain constantly to the supervisor in my area and he brought at least 2 blue boxes to my door. This is in High park. After the big bins came in, and mechanization took hold the city service improved. This was due to mechanization and the reduction of city employees. Though it is still difficult to get large items picked up by city employees,but this provides more work for private "junk companies" of course.As it is probably meant to do.
Sigh replying to a comment from steve / March 29, 2011 at 04:43 pm
user-pic
Steve + Matt = morons
Scoot / March 29, 2011 at 04:54 pm
user-pic
Sanscon was the lowest bidder for the job-Fact. The city takes the lowest bid on all outside contract jobs. The penalty for not meeting the deadline is $500 a day-Fact. As for parking I continue to hear that we have only lost 18-20 spots but they didnt take into consideration that the new spots on the west side have fire hydrants on everyblock. You are actually going to lose 2 more spots on everyblock. I guess the architects or designers cannot read a drawing. This project is on summer 3 so we will see if they finish by July 4th. I asked a city manager if they will be done by July and he said no way. So now we wait and see.
lowrez replying to a comment from jerry / March 29, 2011 at 05:11 pm
user-pic
Because they're true. Ha!
Scoot / March 29, 2011 at 05:20 pm
user-pic
Also the interlocking brick that was already put down on some of the street has to be pulled up and redone....drumroll...cause the work was shitty. The brick is a mess after one winter and imagine the sidewalks after 5-10 years? The maintenance program is for only 2 years. Who lays brick on city sidewalks where snow plows drive on????
oldsalty replying to a comment from J.S. / March 29, 2011 at 05:24 pm
user-pic
JS: Depends on how you slice and dice the numbers. Not all parking spaces are the same. Location matters. I think it is unwise to make those bump-out spaces single-use (streetcar exit/entry) to the exclusion of temporary parking for deliveries and quick customer run-ins. The percentage of parking spaces lost around the United Church because of two bump-outs across from each other plus lost spaces in front of the Library is much, much higher than 8%.
Monty replying to a comment from J.S. / March 29, 2011 at 05:31 pm
user-pic
J.S. I should clarify as I was specifically referring to the area south of Howard, where you can't park due to the tracks being to close to the curb. That would be the entire stretch to the TD bank. That will account for about 15 of your 18 spots right there if that was the plan.
PDG / March 29, 2011 at 05:37 pm
user-pic
According to staff in a local restaurant, many of the 'workers' on this project spend as much time as they can drinking alcohol in local establishments.
John / March 29, 2011 at 05:58 pm
user-pic
I live on Ronci.

Go to Google street view and look at the south end of Ronci. The construction has been going on so long its on Google street view! It's that old.

There have been plenty on months in the last 2 years when the weather was good and nothing was happening on the street. Sanscon dragged it all out and took the city for a ride, wrecking what was once a westend gem of a street.

F-the Polish Fest, that's in SEPTEMBER!!! What about another summer waisted by clouds of smoke and dust, early morning jackhammering, cut gas lines and water mains, and dangerous walking and driving.

Where do the owners of Sanscon live? Let's find out. Let's get a street address.

:)
Rich replying to a comment from PDG / March 29, 2011 at 06:02 pm
user-pic
Not a big surprise is it? And its not alcohol they're drinking, its milk from the public teet.
You all dumb / March 29, 2011 at 06:28 pm
user-pic
It seems that instead of fighting the city and its contractors on this sort of issue, you are all content to fight with each other in the comment thread. How dumb. Progressive city we live in, eh!! Let us instead band together in these public forums and demand change from the City of Toronto - people lost their livelihood over this mess. Let us not trivialize that with petty bickering.
steve replying to a comment from PDG / March 29, 2011 at 06:34 pm
user-pic
Wasn't there recently a discussion about lazy city workers? It was to justify contracting out and privatizing.
Interesting!
Looks like the private sector are the lazy ones suckling at the teat of the taxpayer.
John / March 29, 2011 at 07:10 pm
user-pic
"You all dumb" has it right. Ronci folk are nice, accepting people. Maybe too much so. If we had been down at city all bitching every day like the St. Clair people, maybe it would be done by now. Lesson: Be a jerk. Sad.
Steph replying to a comment from steve / March 29, 2011 at 07:13 pm
user-pic
I notice that the Ronces TTC work was done on time -- and they use their own crews, not private contractors
Tim / March 29, 2011 at 08:57 pm
user-pic
I live in the hood. I watched this gong show first hand. There were weeks that went by with zero work being completed as shops and restaurants closed. We didn't want it done to begin with but Gringo Gord Perks jammed it down city hall's throad. Millionaire Socialist
Tim replying to a comment from mike / March 29, 2011 at 08:58 pm
user-pic
Dildo - Sanscom is a private company awarded by Miller.
Miranda / March 29, 2011 at 09:02 pm
user-pic
Is there a daily quota of blog-titles-in-question-form that you guys need to fill?
Antony replying to a comment from Tim / March 29, 2011 at 10:54 pm
user-pic
It's being a "millionaire socialist" to replace water and gas mains, and re-build worn-out streetcar tracks?

I swear there's a 12-card deck of angry right wing slurs that's randomly used to insult others.

Got to love the private sector, looking after their bottom line.
Marc / March 30, 2011 at 01:50 am
user-pic
Two words: THIRD WORLD
gadfly / March 30, 2011 at 07:56 am
user-pic
Don't care: never drive through there. Never would. The area has nothing to offer, crappy parking, dumpy stores. I did notice the rusting streetcar tracks piled high on King St that sat there for years, blocking a lane of traffic. City could care less about that - they're for the blessed streetcars, after all.
Why couldn't they have leveled the entire place and put a big box store area, with a direct ramp off the Gardiner? That would have been an improvement.
Joking aside, the city's incompetence is not limited to Ronscesvales or St. Clair: from planning on up to completion the city could not run a popsicle stand. Name one project that has EVER come in on time or on budget, private or public sector. It doesn't matter. The private contractors know the city does nothing and the city employees cannot be fired. It's the same middle and upper managers that screw it up every time.
tuk tuk / March 30, 2011 at 08:25 am
user-pic
Whiiiiiiiiiiiiiiine
scottd replying to a comment from Rich / March 30, 2011 at 08:38 am
user-pic
Nothing I have read here or seen supports your rush to judge.
scottd / March 30, 2011 at 08:51 am
user-pic
I dont now why people start talking about kickbacks every time a story comes up but it is really lazy. No is zero evidence of this in this case and even if there was, how would that delay the project? Armchair expert.

As was reported the City strike had a large impact that could not have been foreseen. That delay has been documented and documented.

MOnty> You are completely wrong about parking and I would add that I have had no trouble finding parking on Roncy during the construction. The new parking configuration was approved by the local BIA and fits their existing parking plans. Here is some knowledge in their own words....

"While Green P has recently added some parking capacity to Roncesvalles, it is clear that this plan would change Roncesvalles into a street that prioritizes transit, cycling and pedestrian uses over car traffic and parking. This is in line with new city policy, as well as the BIA’s streetscape strategy of 2003. While the BIA would like to preserve parking where possible, the plain fact is that Roncesvalles will never be able to compete with other shopping areas on parking availability. To compare, Roncesvalles currently has perhaps 200 on-street parking spaces, while Yorkdale Mall has 7,200. But Roncesvalles can offer something that a mall never can: a pleasant and distinct experience for shoppers who walk, cycle or ride the streetcar."

Lets wait until it is finished before we start making grand accusations about how it has turned out.




Charles replying to a comment from scottd / March 30, 2011 at 09:00 am
user-pic
"Lets wait until it is finished before we start making grand accusations about how it has turned out."

I'd love to wait for them to finish to comment as you've suggested... so far I've waited 3 years. Let me know how much longer I have to wait before I have your permission to pass judgment you tool.
Matt / March 30, 2011 at 09:46 am
user-pic
Folks: The project isn't even over yet. Maybe wait to see how traffic (including pedestrian, transit and cyclist traffic) and parking work when everything is in place and the P meters are back in action. My bet is that business revenues and property values will go up as a result of the neighbourhood being even more pedestrian friendly than it already was.

The only negative spin-off that I can foresee is the chance that traffic will divert heavily to Sorauren, but I'm hoping that over time, people who aren't commuting locally will learn to use Parkside, Lansdowne and the new and improved Dufferin for their north-south travel.
mike in parkdale replying to a comment from Matt / March 30, 2011 at 10:53 am
user-pic
"The only negative spin-off that I can foresee is the chance that traffic will divert heavily to Sorauren..."

agreed 100%

And another issue that people often overlook is that when a street like Roncy becomes impassible, all the traffic moves to smaller side streets and causes more congestion and noise on strictly residential streets. The entire area is effected, and not just the street under construction.
ttraveller / March 30, 2011 at 11:03 am
user-pic
Got to love the wonderful "let's not rush to judgement and wait to see it all turn out roses", folks. So typically Toronto- Rearranging the deck chairs on the sinking titanic. As with St. Clair, this is a project rammed down the throats of local citizens by Counselors with God complexes and implemented by incompetent and uncaring bureaucrats. Residents of Ronces, what you see is nowhere near the end. As with St. Clair, you have many years left to enjoy the unfolding fiasco.
Vi replying to a comment from Matt / March 30, 2011 at 11:50 am
user-pic
Which one is that, Matt? I live in the area and I've been wondering about the new sushi places. Yumm...
agentsmith / March 30, 2011 at 01:12 pm
user-pic
It's hilarious that so many of you think the fundamental problem here is private contractors. If you really think a bunch of bureaucrats and City employees could do it faster and cheaper, you haven't got a clue.

With private contractors, there's actually an incentive to complete projects on time and control costs. If the penalties for not meeting deadlines aren't high enough to give the proper incentive, then simply make them higher. If it was done publicly with City workers, there would be no incentives whatsoever in the first place.

And as other commenters have pointed out, probably the biggest issue was lack of coordination between City departments. No surprise there, and hardly the fault of the contractor. I'm not saying the contractor is blameless, but he's certainly not the only bad guy here.
Paul / March 30, 2011 at 02:52 pm
user-pic
When one realizes that the CPR was constructed clear across the wilderness of an untouched continent using relatively primitive tools & resources...and in a relatively short period of time...one must wonder why these modern urban street construction projects seem to take bloody well forever.
Gloria / March 30, 2011 at 04:47 pm
user-pic
I worked in procurement with a provincial government Ministry for 1 1/2 years over 20 years and I know it was kickbacks when I worked with a mother and son team(not allowed)and the roomate of the mistress of the general manager and 1/4 to 1/3 of the invoices had no purchasing orders or bills of lading attached. They were allowed to purchase 23 million, spent 31 million. I spent most of my time hunting down who had ordered the item, which no one admitted to. One interesting item was a recent grad who had worked in purchasing and then moved to marketing even tried to strongarm me to signoff the purchase of $250,000 of mixed Workperfect and Lotus software packages. And then he tried it with my controller. Then someone called the purchasing manager for the dept, but apparently they didn't make the right approach as there was a lot of swearing. Then a freedom of information request was filed. All the items on a $50,000 invoice were the wrong quantity, quality, price. The same $50,000 invoice was paid 3 times. The director of purchasing for the ministry was not fired but went on to bigger and better things at the Toronto School board and is now VP, Strategic Purchasing at a well known financial services company. And he still advises government on how to purchase, his way.
Danny / March 30, 2011 at 08:29 pm
user-pic
"Got to love the wonderful "let's not rush to judgement and wait to see it all turn out roses", folks. So typically Toronto- Rearranging the deck chairs on the sinking titanic."

Because taking a rational, level-headed approach to problems is a less desirable approach to your hysteria, hyperbole and emotional overreaction?
Patrick replying to a comment from Gloria / March 30, 2011 at 10:27 pm
user-pic
"Councillor Perks is an unusual person. As a taxpayer I want the cheapest bid, or should we go for the highest?"

I never realized that the alternative to arbitrarily picking the lowest bid that Councilor Perks is suggesting is to arbitrarily pick the highest.

It is quite amazing to learn that these are the only two possible options.

agentsmith / March 31, 2011 at 09:30 am
user-pic
I'm not sure they're absolutely required to take the lowest bid anyway. It's probably more a matter of the City just not bothering to analyze the bids.
Gloria / March 31, 2011 at 12:36 pm
user-pic
Well, having worked in purchasing I know that the lowest bidder gets the business. It's better than the vendor's partner or mother-in-law getting the business, which was the situation at the ministry I worked at. The purchasing agent's partner had the contract and could go into the warehouse and change the items on a bill of lading which had been incorrectly recorded. Maybe you would prefer this system
Eric S. Smith / March 31, 2011 at 04:51 pm
user-pic
Come off it, Gloria. The alternative to a system that uncritically falls for the very lowest bid even when that bid <i>is a lie</i> is not the nightmare scenario that you're so breathlessly evoking. It might involve disqualifying bidders who've been shown not to be able to deliver, or requiring stronger proof that the work can be completed on time at the proposed price.

"Having worked in purchasing," you would, I am sure, have seen the occasional too-good-to-be-true price.
agentsmith replying to a comment from Gloria / March 31, 2011 at 05:19 pm
user-pic
Yes, because the only alternative to taking the lowest bidder is fraud. Give your head a shake.

The point is, the lowest bidder should not automatically get the contract. Anyone who operates like that is simply too fucking lazy to read more than just the grand totals on the bids. And when they get burned, they deserve it.
jeff replying to a comment from Matt / April 6, 2011 at 04:57 pm
user-pic
Matt that is not so.

The city builds in to every contract a performance bond. If you do not do the job correctly they can step in and get it done.

Plus they will NOT pay you under contract unless you have met certain criteria such as levels of completion.

The reality is Perks is whitewashing the entire mess protecting city/union staff.

The single biggest problem with EVERY city project these days is city staff. They have a poor work ethic, often little practical experience on a construction site and they are lax to do anything to press a job forward because then the city can be liable. The mantra from the legal department is 'find the slightest infraction to shift liability away from the city'. With orders such as that there is zero incentive for staff to help in any way.
ttraveller replying to a comment from jeff / April 7, 2011 at 12:02 pm
user-pic
Totally agree based on my practical experience. Also a big issue is the quality of the bidders. The high quality bidders know about the nightmare of dealing with the City and build this into their price. In Toronto we get the lowest bidder we deserve.
ml / April 10, 2011 at 12:17 pm
user-pic
As a person responsible for dealing with contractors on a regular basis, I have learned from many mistakes. First lesson, take the lowest bidder and the highest bidder and toss those in the garbage. Now take everyone in between and check their references THOROUGHLY. Whether it's a five thousand dollar job or a 5 million dollar job, this is bible.
When you pay peanuts you get monkeys.
ttraveller replying to a comment from Danny / April 11, 2011 at 01:06 pm
user-pic
Ah the slow motion denial of the sinking Ronces Titanic. See today's Star for how well the "rational, level headed" folks have done so far http://www.thestar.com/news/article/972515--roncesvalles-ave-faces-one-more-torn-up-spring?bn=1

gr1 / April 11, 2011 at 11:14 pm
user-pic
KILL EM ALL LET PERKS SORT EM OUT. tm

Add a Comment

Other Cities: VancouverMontreal